Page 10 - 4925
P. 10

The operator may make additional preparations before moving in the rig. The
            terrain, the well’s depth, the underground pressures expected, and the operator's and
            contractor's preferences determine  how they start the well.  At  land sites where the
            operator has ordered a deep, high-pressure well, for example, a work crew, using dirt
            moving equipment, may dig a rectangular pit, or cellar. Sizes vary, but a typical cellar
            is about 10 feet (3 metres) on a side and perhaps 10 feet (3 metres) deep. The exact
            size and depth depend on the characteristics of the well and the rig's configuration.

                   Sometimes, the workers line the cellar with boards or pour concrete walls to
            keep it from caving in. The cellar accommodates a tall stack of high-pressure control
            valves under the rig. The bottom of the stack will sit in the cellar, below ground level.
            Since the crew installs the stack below ground level, the rig’s substructure – the base of
            the rig – does not have to be as tall to allow the rig floor to clear the stack. In short, a
            cellar provides more working room under the rig.

            Rathole

                   Some rigs use a special pipe called the “kelly," which is part of the drill string.
            The kelly is part of the system that rotates the bit. Rigs with kellys require a rathole –
            a  shallow  hole  drilled  off  to  the  side  of  the  main  borehole.  On  land,  the  operator
            sometimes hires a special truck-mounted, light-duty unit called a “rathole rig” to drill
            the rathole. Or, after the rig is set up (rigged up), the drilling crew may drill the rathole
            with  special  equipment.  Offshore,  if  the  rig  needs  a  rathole,  it  is  a  large-diameter
            length of pipe that extends below the rig floor. In the case of drilled ratholes, the crew
            extends pipe from the drilled part of the rathole up to the rig floor. The rathole goes
            through the rig floor and protrudes a few feet, or a half metre or so, above it.
                   During drilling, the crew uses the rathole to store the kelly temporarily. A kelly
            can be up to 54 feet, or 17 metres, long. Even the tallest land rig substructures are
            only about 40 feet(12 metres) high and most are even shorter. The contractor there-
            fore  has  to  drill  part  of  the  rathole;  otherwise,  the  rathole  would  extend  too  high
            above the rig floor to be accessible.

            Mousehole
                   The rathole rig or the main rig itself may also drill a mouseholeon land sites. A
            mousehole, like a rathole, is also a shallow hole lined with pipe that extends to the rig
            floor. The mousehole is a lined hole into which the crew puts a length, or joint, of drill
            pipe during drilling operations. When crew members are ready to add the joint to the
            drill string as the hole deepens, they add it from the mousehole. A joint of drill pipe is
            around 3o feet (9 metres) long. If the regular rig’ssubstructure is appreciably shorter
            than this height, then the rathole crew also drills a mousehole.

            Conductor Hole

                   The rathole crew may also drill the first, or top, part of the main borehole. The
            operator can, in some cases, save time and money by having the rathole rig actually
            start, or spud, the main hole before moving in the regular rig. The rathole crew backs
            the rathole rig to the cellar. A special bit starts the  main hole in the middle of the
            cellar. This hole is shallow in depth but large in diameter. Termed conductor hole, it

                                                                                                            9
   5   6   7   8   9   10   11   12   13   14   15