Page 46 - 6634
P. 46
Non-generated loads (equipment and supplies- wet/dry -, empty area
loads, live loads, dynamic vibrations from rotating machinery, mud
pumps and operations, etc.),
Design life (operating and fatigue),
Accidental design loads (boat impact, dropped objects, fire and blast),
Load combination cases (extreme environmental, operational,
serviceability, transportation, lift and launch),
Damaged stability and or redundancy requirements (missing member,
flooded leg or compartment),
Preferred material classes,
Design regulations, codes and recommended practices,
Appurtenances and their locations (escape and evacuation equipment,
escape ways, stairs. boat landings, barge bumpers, conductors and J-
tubes, mud-mats, etc.),
Corrosion protection requirements (type-anode, impressed current- and
life),
A narrative of construction methods and procedures that will have an
impact on the platform configuration and sizes (skidding and load-out
procedures, pulling points, lifting eyes, launch skids etc.),
Verification and certification requirements,
Any other owner requirements that will impact detailed design (jack-up
drilling unit clearances, tender rig sizes and weights.
Detailed design (also called by some as the “execute engineering phase” or
“final design phase”) includes all engineering analyses; approved for construction
(AFC) detailed design drawings, specifications, procedures and reports required to
allow fabrication, transportation, installation, pre-commissioning, HUC, startup
and operations of a platform.
1. Engineering analyses include all design conditions:
46