Page 50 - 6634
P. 50
* As the size of a jacket structure increases, it is built and transported on a
cargo barge in the horizontal position. The jacket is lifted off the cargo barge
using one or two cranes. Following pick-up, the cargo barge is withdrawn
and the jacket is upended. Single cranes with two blocks can be used for
upending smaller jackets with the jacket length aligned with the plane of the
crane boom. There are several methods of upending jackets:
* Two-block upending - upending in air or partially in water using two crane
blocks. In this method, the jacket does not have sufficient buoyancy to float
without crane assistance. Instead, the upending is achieved by hoisting down
the block of one of the two cranes while the other is hoisted up. Figure 4.2
shows a two-block upend operation. The size of the jackets that can be
upended with a single crane is limited.
Figure 4.2 – Two block upending
Single-block upending. A jacket installed using this method needs to have
sufficient buoyancy to float in the horizontal position by itself. In this method, the
50