Page 66 - 6200
P. 66

Cellar

                   The operator may make additional preparations before moving in the rig. The terrain, the
            well’s depth, the underground pressures expected, and the operator's and contractor's preferences
            determine  how  they  start  the  well.  At  land  sites  where  the  operator  has  ordered  a  deep,  high-
            pressure well, for example, a work crew, using dirt moving equipment, may dig a rectangular pit, or
            cellar. Sizes vary, but a typical cellar is about 10 feet (3 metres) on a side and perhaps 10 feet (3
            metres)  deep.  The  exact  size  and  depth  depend  on  the  characteristics  of  the  well  and  the  rig's
            configuration.

                   Sometimes, the workers line the cellar with boards or pour concrete walls to keep it from
            caving in. The cellar accommodates a tall stack of high-pressure control valves under the rig. The
            bottom of the stack will sit in the cellar, below ground level. Since the crew installs the stack below
            ground level, the rig’s substructure – the base of the rig – does not have to be as tall to allow the rig
            floor to clear the stack. In short, a cellar provides more working room under the rig.
            Rathole
                   Some rigs use a special pipe called the “kelly," which is part of the drill string. The kelly is
            part of the system that rotates the bit. Rigs with kellys require a rathole – a shallow hole drilled off to
            the side of the main borehole. On land, the operator sometimes hires a special truck-mounted, light-
            duty unit called a “rathole rig” to drill the rathole. Or, after the rig is set up (rigged up), the drilling
            crew may drill the rathole with special equipment. Offshore, if the rig needs a rathole, it is a large-
            diameter length of pipe that extends below the rig floor. In the case of drilled ratholes, the crew
            extends pipe from the drilled part of the rathole up to the rig floor. The rathole goes through the rig
            floor and protrudes a few feet, or a half metre or so, above it.
                   During drilling, the crew uses the rathole to store the kelly temporarily. A kelly can be up to
            54 feet, or 17 metres, long. Even the tallest land rig substructures are only about 40 feet (12 metres)
            high and most are even shorter. The contractor therefore has to drill part of the rathole; otherwise,
            the rathole would extend too high above the rig floor to be accessible.
            Mousehole
                   The rathole rig or the main rig itself may also drill a mousehole on land sites. A mousehole,
            like a rathole, is also a shallow hole lined with pipe that extends to the rig floor. The mousehole is a
            lined hole into which the crew puts a length, or joint, of drill pipe during drilling operations. When
            crew members are ready to add the joint to the drill string as the hole deepens, they add it from the
            mousehole. A joint of drill pipe is around 3o feet (9 metres) long. If the regular rig’s substructure is
            appreciably shorter than this height, then the rathole crew also drills a mousehole.

            Conductor Hole
                   The rathole crew may also drill the first, or top, part of the main borehole. The operator can,
            in some cases, save time and money by having the rathole rig actually start, or spud, the main hole
            before moving in the regular rig. The rathole crew backs the rathole rig to the cellar. A special bit
            starts the main hole in the middle of the cellar. This hole is shallow in depth but large in diameter.
            Termed conductor hole, it may be 36 inches (91 centimetres) or more in diameter. It may be only
            tens  of  feet  (or  metres)  deep or  it  may  be  hundreds  of  feet  (or  metres)  deep,  depending  on  the
            surface conditions.
                   The rathole crew lines the conductor hole in the cellar with conductor pipe. Conductor pipe,
            or casing, keeps the hole from caving in. It also conducts drilling mud back to the surface when
            regular drilling begins. The crew often secures the conductor pipe in the hole with cement or con-
            crete. With the conductor pipe, rathole, and mousehole prepared, the drilling contractor can move in
            the rotary rig to drill the rest of the hole.

            Other Considerations
                   On drilling locations where the ground is soft, a rathole rig and crew may not be needed.


                                                                                                          42
   61   62   63   64   65   66   67   68   69   70   71