Page 40 - 6748
P. 40

we  want  to  avoid  that  situation.  Engineer  1:  Sure.  But  after  saying  that,  if  someone  has  to
                  analyse every single revision to determine exactly which team needs it, then that takes a lot of
                  time as well.
                  Leo: Not if there's a proper procedure in place.
                  As long as we make sure there’s ...

                  2
                  Leo:  This  project  strikes  one  as  pretty  complex,  in  terms  of  the  amount  of  integration  and
                  overlap between the different design packages.
                  Engineer 1: Yeah.
                  Leo: Particularly between mechanical and electrical teams so we have to coordinate that. And
                  it's obviously a specialist job. It’s beyond my expertise as the overall project manager. So, in
                  order to make sure that we ...

                  3
                  Leo:  Thinking about how the separate design groups  work together, I don't  want to rely too
                  much on scheduled meetings. We don't  want questions and problems piling up, waiting to be
                  resolved at a meeting in a week's time, or whenever. You all need to be talking to one another on
                  an ongoing basis.
                  Engineer 2: I agree with what you're saying.
                  The trouble is, when you're trying to sort out problems with details on drawings and that kind of
                  thing, you need to meet face-to-face. And given that we all  work in separate offices, it's, you
                  know, we can phone each other, but...
                  Engineer 1: Yeah, you still need meetings.
                   Engineer 2: Especially as there’s so much integration between the different packages, the point
                  we were talking about before.
                  Leo: Well, there is a solution to the problem.

                  d  ►4.5 Read Leo summarising the solutions that have been agreed in the meeting. What
                  has been decided regarding the following points?
                  1      The decision that the senior engineer in each team must make, regarding drawings
                  2      The circulation procedure that will be used for each drawing
                  3      The  role  of  the  M&E  coordinator  in  relation  to  the  senior  engineers  and  the  project
                  manager
                  4      The arrangement that will make informal communication easier


                  Leo: So, to sum up. As regards design information flow, all preliminary drawings are going to
                  be shown to the senior engineer in charge of each design team. The senior engineers then say
                  whether or not their teams need to receive copies of later revisions. If they don’t, they won’t
                  receive any further revisions. If they do, they'll be issued with every subsequent revision and,
                  later,  revisions  of  working  drawings.  To  coordinate  the  interface  between  mechanical  and
                  electrical design, I'm going to appoint a mechanical and electrical coordinator responsible for
                  liaising  between  the  senior  engineers  in  the  teams,  reporting  to  me.  We're  locating  all  three
                  design teams in a single, open-plan office so when anyone's got a question or a problem, they
                  can  talk  to  the  appropriate  person  face-to-face.  We  still  have  scheduled  meetings  to  discuss
                  formal issues, but the emphasis will be on ongoing, informal dialogue between the teams.

                  e  In pairs, discuss how the design procedures discussed in the meeting will work in the
                  following situations.


                                                                                                             38
   35   36   37   38   39   40   41   42   43   44   45