Page 49 - 4924
P. 49
d) no correct answer.
24. The crew stabs the end of the new joint into the joint suspended by the slips in
the … , and, using a spinning wrench and the tongs, they thread the joints
together and buck them up to final tightness.
a) mousehole;
b) rotary table;
c) fingerboard;
d) no correct answer.
25. Should the top drive fail, the driller can rotate the string and bit with … .
a) rotary table;
b) fingerboard;
c) rotation casing;
d) no correct answer.
26. The latest equipment to pull pipe out of the hole, as well as to run it in, is an
automatic … device.
a) pipe-lifting;
b) pipe-handling;
c) pipe-screwing;
d) no correct answer.
27. Because the drilling crew just drilled the surface hole, the first string of casing
run into the hole is called "…," or "surface pipe."
a) hole casing;
b) surface casing;
c) surface hole;
d) no correct answer
28. Casing is strong … pipe.
a) iron;
b) potassium;
c) steel;
d) no correct answer.
29. Running casing into the hole is … to running drill pipe, except that the casing.
a) the same;
b) completely different;
47