c) sand;
                   d) no correct answer.


                   13. Special high-pressure pumps move the slurry through very strong … , or lines,
                      to a cementing head, or plug container.
                   a) pipes;

                   b) casing;
                   c) cementing tube;
                   d) no correct answer.


                   14. As the last of the cement … enters the casing, a crew member releases a
                      topping from the cementing head.

                   a) slurry;
                   b) solution;
                   c) fluid;
                   d) no correct answer.


                   15. Displacement fluid, which is usually … water or a specially formulated drilling
                      mud, moves, or displaces, the cement from the casing as the cement pump

                      applies pressure to move the cement and fluid down the casing.
                   a) mineral;
                   b) salt;

                   c) organic;
                   d) low-carbonated.


                   16. Continued pumping moves the cement, the top plug, and the displacement fluid
                      … the casing.
                   a) down;
                   b) up;

                   c) up and down;
                   d) no correct answer.


                   17. With the kelly made up, the driller starts the mud pump, … the kelly drive
                      bushing to engage the master bushing.
                   a) raises;

                   b) lowers;
                   c) inserts;
                   d) no correct answer.