from the well under all drilling conditions. When the drill string is
           in  the  hole,  movement  of  the  pipe  without  releasing  the  well
           pressure should  be allowed to occur. In addition, the BOP stack
           should  allow  fluid  circulation  through  the  well  annulus  under
           pressure.  These  objectives  usually  are  accomplished  by  using
           several ram preventers and one annular preventer (Fig. 12.1).













































                       Figure 12.1 – Stack of blowout preventers