In a slot-type jack-up, the platform has a slot through the
                            floor  of  the  hull.  A  drilling  derrick  is  positioned  over  it  during
                            operations.  When  the  platform  moves  to  another  location,  the
                            derrick is lifted above it.
                                  Drilling Systems
                                   Drilling system is the heart of the jack up rig. Drilling is
                            carried out at the drill floor which is at certain elevation from the
                            main deck. There is a mouse hole and rat hole in which the drill
                            stems  are  assembled.  Once  the  stem  is  assembled  it  is  placed
                            concentric with the rotary table which is either driven from the top
                            or from the bottom. Kelly bushing is provided to support the drill
                            stem and prevent it from buckling.
                                   The  top  drive  (fig.  1.10)  rotates  the  drill  string  end  bit
                            without  the  use  of  a  kelly  and  rotary  table.  The  top  drive  is
                            operated from a control console on the rig floor.
























                                                     Figure 1.10 -- Top Drive
                                  Mud Systems
                                   These are of two types – high pressure mud system and low
                            pressure mud system.
                                    Mud  is  a  mixture  of  raw  water,  clay,  bainite  and  some
                            other minerals. Working of the jack up rig depends upon the power
                            of the mud system. It is a cyclic procedure which is used to convey
                            the crushes from the bottom of drill bits to the top of mud tanks
                            (fig.  1.11).  This  is  called  high  pressure  mud  system.  when  we