b) pipe
c) case
d) no correct variant
8. What does a cementing company do?
a) offers special support to the drilling operation
b) cements the casing in the well
c) cements equipment
d) no correct variant
9. Is that true that personnel live as well as work offshore or in isolated regions for
long periods of time?
a) no
b) yes
c) no correct variant
10. The rig superintendent supervises the driller, who, in turn, supervises …
a) the derrickman
b) the toolpusher
c) the other driller
d) no correct variant
11. If the crews work … tours on land, then the contractor may hire two drilling
crews and two superintendents for each rig.
a) 6 -hour
b) 12 -hour
c) 8 –hour
d) no correct variant
12. The contractor mounts the monkeyboard in the mast or derrick at a height
ranging from about …
a) 20 to 40 metres
b) 15 to 34 metres
c) 30 to 50 metres
d) no correct variant
13. The person in charge of the drilling crew, the top hand, may be called the “rig
manager”, “rig superintendent”, or …
a) “boss”
b) “toolpusher”
c) “rig director”
d) no correct variant
14. Besides the rig manager, or superintendent, each rig has drillers, derrickmen,
and …
25